How Should Fragrance Distribution Lines Be Planned for a Multi-Level Scent Diffuser Machine Project?

2026-11-17

A hotel group specifies a single Scent Diffuser Machine for a four level lobby and corridor system. The machine is sized correctly, the fragrance is selected, and the installation is completed. When the system is commissioned, the ground floor lobby is over scented and the top floor corridor has almost no fragrance. The machine is blamed, but the machine is not the problem. The distribution line was designed as a single long run without a riser calculation, and the pressure drop through the vertical section consumed most of the available output. Our engineering team has seen this pattern in multi level projects, and we plan the distribution lines before the machine is selected. Shenzhen Scentsea Technology Co., Ltd. has been designing multi level scenting systems for over 10 years.

Aluminum Home Scent Diffuser Machine



1. Why Must the Distribution Line Be Planned Before the Machine Is Sized?

The distribution line is not an accessory. It is part of the pneumatic circuit. The Scent Diffuser Machine produces a small positive pressure at the outlet, and that pressure must overcome the friction loss in the tubing, the fitting loss, the vertical lift loss, and the discharge loss at the outlet. If the line is long or if the riser is tall, the available pressure at the outlet is reduced, and the fragrance output drops. A machine that is sized for a 10 meter run will not deliver the same output on a 40 meter run with a 15 meter riser. This is why our factory asks for the floor plan and the riser height before we recommend a machine model. The line design and the machine selection must be made together.


The line design also determines the number of zones. A single machine can serve several zones if the line is fitted with solenoid valves that open and close in sequence. The zoning allows the fragrance to be delivered to the occupied areas at different times, which reduces the total fragrance consumption and improves the consistency. A line that is planned without zoning will deliver fragrance to all areas at the same time, and the areas with lower loss will be over scented.


2. How Is the Required Tube Diameter Calculated for Each Riser and Branch?

The tube diameter is selected from the flow rate and the allowable pressure drop. The flow rate is set by the machine output and the number of active outlets. The allowable pressure drop is set by the machine outlet pressure minus the discharge pressure required at the outlet. A smaller tube has a higher friction loss and a lower cost, while a larger tube has a lower friction loss and a higher cost. The calculation should be performed for the longest run and the highest riser, because these are the critical paths. The table below shows the typical pressure loss for common tube sizes at a low fragrance flow rate.


Tube outer diameter Flow rate Pressure loss per 10 m horizontal Pressure loss per 10 m vertical Typical use
6 mm 2 to 4 liters per minute 0.8 to 1.5 kPa 0.1 to 0.2 kPa plus static head Single outlet, short branch
8 mm 4 to 8 liters per minute 0.5 to 1.0 kPa 0.1 to 0.2 kPa plus static head Two to three outlets
10 mm 8 to 15 liters per minute 0.3 to 0.6 kPa 0.1 to 0.2 kPa plus static head Main riser and main branch
12 mm 15 to 25 liters per minute 0.2 to 0.4 kPa 0.1 to 0.2 kPa plus static head Long riser and multi zone main


The static head is the pressure required to lift the fragrance vapor to the highest outlet. The static head is small for a vapor, but it must be included because the vapor density is not zero. Our factory prepares a pressure loss table for each project, and we recommend the tube size that keeps the total loss below 60 percent of the machine outlet pressure. Shenzhen Scentsea Technology Co., Ltd. provides the pressure loss calculation with each multi level quotation.


3. How Should the Vertical Riser and Horizontal Branch Be Arranged to Keep the Zones Balanced?

The riser should be as short and as straight as possible. Every bend adds a fitting loss, and every horizontal offset adds friction. The riser should be placed in a service shaft or a wall cavity that is accessible for inspection, and it should be supported at intervals to prevent sagging. The horizontal branches should be taken from the riser at each floor through a manifold, not through a series of tees along the riser. A series of tees creates a different pressure at each branch, and the lower branches receive more fragrance than the upper branches. A manifold at each floor equalizes the pressure and makes the balancing easier. The table below shows the arrangement options and their effect on balance.


Arrangement Balance across floors Balancing effort Service access
Single riser with series tees Poor, lower floors over scented High, each branch needs a valve Difficult, tees are inside the wall
Single riser with floor manifolds Good, manifold equalizes pressure Moderate, one valve per floor Good, manifold is in a service box
Dual riser with zone valves at the machine Very good, zones are independent Low, zones are controlled at the machine Good, service is at the machine room
Dedicated machine per floor Excellent, each floor is independent None, no balancing required Excellent, service is local



System designer's note: The dual riser arrangement with zone valves at the machine is the best compromise for a building with four to eight floors. The riser is still required, but the zones are controlled at the machine room, and the balancing is performed with the zone valves. Our factory supplies the zone valve manifold and the control board for this arrangement. Shenzhen Scentsea Technology Co., Ltd. can also supply a dedicated machine per floor when the building has a very large footprint or when the riser route is not available.



4. Which Materials and Connections Prevent Fragrance Absorption and Leakage?

The tubing material must be compatible with the fragrance oil and the carrier gas. Some plastics absorb the fragrance and release it slowly, which changes the scent profile and wastes oil. The tubing should be made from PTFE, FEP, or a fragrance resistant nylon. The fittings should be push to connect or compression type, and they should be tested for leak tightness at the operating pressure. The tubing should not be transparent if it is exposed to sunlight, because the UV can degrade the fragrance. The table below shows the material options and their suitability.


Material Fragrance absorption UV resistance Typical use
PTFE Very low Good Main riser, critical branch
FEP Low Good Branch and outlet connection
Fragrance resistant nylon Moderate Moderate Short branch inside a wall
Standard PVC High Poor Not recommended


Our factory uses PTFE for the main riser and FEP for the branch and outlet connection. The fittings are push to connect with a double O ring, and they are tested at 100 kPa for 10 minutes before the line is closed. We also install a drain valve at the lowest point of the riser so that the line can be purged during service. Scentsea supplies the tubing, the fittings, and the purge kit as a single package for each project.


5. How Should the System Be Commissioned and Balanced After Installation?

The commissioning has three steps. The first is the leak test. The line is pressurized with dry air at 100 kPa and held for 10 minutes, and every joint is checked with a leak detection solution. The second is the flow test. Each outlet is measured with a flow meter, and the zone valve is adjusted so that each outlet receives the design flow. The third is the scent intensity test. The fragrance is released in each zone, and the intensity is measured with a handheld sensor or assessed by a panel. The zone valve is adjusted again so that the intensity is uniform across the zones. Our factory provides a commissioning sheet that lists the target flow, the measured flow, the target intensity, and the measured intensity for each outlet. Shenzhen Scentsea Technology Co., Ltd. can provide a commissioning engineer for large projects.


The commissioning should be repeated after any change to the line, such as a new branch or a new outlet. A line that is balanced at the factory may not be balanced after the installation, because the actual riser height and the actual branch length may differ from the drawing. The commissioning sheet should be kept with the system manual so that the balancing can be repeated when the system is serviced.


Frequently Asked Questions About Fragrance Distribution Lines in Multi-Level Projects

Question 1: Can a single scent diffuser machine serve multiple floors in a tall building?
Answer: A single Scent Diffuser Machine can serve multiple floors, but the number of floors is limited by the pressure loss in the riser and the total flow required by the outlets. For a building with four to six floors and a normal riser height, a single machine with a dual riser and zone valves is usually adequate. For a taller building or a building with a large floor area, a dedicated machine per floor is more reliable, because the riser loss is eliminated and each floor can be controlled independently. The system designer should calculate the pressure loss for the critical path before deciding.
Question 2: What tube diameter should be used for the main riser in a multi-level project?
Answer: The main riser tube diameter depends on the total flow and the riser height. For a total flow of 8 to 15 liters per minute and a riser height of 10 to 20 meters, a 10 millimeter outer diameter tube is usually adequate. For a higher flow or a taller riser, a 12 millimeter tube is recommended. The designer should calculate the pressure loss at the design flow and confirm that the loss is below 60 percent of the machine outlet pressure. A tube that is too small will starve the upper floors, and a tube that is too large will add cost without improving the balance.
Question 3: How can fragrance absorption in the tubing be reduced?
Answer: Fragrance absorption in the tubing can be reduced by selecting a low absorption material such as PTFE or FEP, by keeping the tubing length as short as possible, and by purging the line after each scenting cycle. A purge cycle uses dry air to push the remaining fragrance out of the tube and into the room, which prevents the oil from sitting in the tube and being absorbed. Our factory supplies a purge kit that includes a solenoid valve and a timer, and we recommend it for any line longer than 20 meters or any line that is used intermittently.

Summary and Recommendation: A multi-level Scent Diffuser Machine project should start with the line layout, not with the machine model. The tube diameter should be calculated for the critical path, the riser should be straight and supported, the branches should be taken from floor manifolds, and the materials should be fragrance resistant. The system should be commissioned with a leak test, a flow test, and an intensity test, and the balancing record should be kept with the manual. When the line is planned correctly, the fragrance is uniform across the floors and the machine operates within its design range.


Need a pressure loss and zoning review for a multi-level scenting project? Contact our engineering team with the floor plan, the riser height, and the target intensity. We will prepare the line layout and the machine recommendation for the project.
Previous:No News
Next:No News

Leave Your Message

  • Click Refresh verification code